On the day prior to the reline, we prepared the UV resin. UV pipe relining is a great option when work needs to be completed quickly. It also cures faster than other resins, meaning the services are reinstated faster, resulting in minimal disruption.
On Saturday (to not disrupt office work), we successfully relined all three cast iron sewer stacks and repaired the sewer vent pipes. This included cutting out ten junctions using robotic junction cutting.
Since the site was a busy business during the week, we undertook the works on the weekend. This ensured minimal disruption to the building occupants and allowed us to complete the cast iron pipe reline as quickly as possible.
The majority of the work was indoors, so we hired an electronic air compressor to ensure the health and safety of our staff and anyone who might be in the building. Works that are completed outdoors can use a standard air compressor that runs on fuel, however to complete an indoor pipe relining project, we needed a compressor that did not emit fumes.
We also needed an electrician to run 3-phase power to the specific location to run the compressor before we started work.
It was a great accomplishment to reline three-fifty metre cast iron sewer stacks with junction cutting in one day! Our team went the extra mile to get this job done on the weekend. They worked together and everything went smoothly.
We were grateful for the help from Fracks Air Compressors, who organised the essential internal air compressor that was needed for this job.
Ready Set Reline provides quality services throughout all stages of pipe and drain relining in Sydney for long lasting pipe repairs. We have a price beat guarantee – contact us for a free quote!
© 2024 Ready Set Reline | Privacy Policy | Terms & Conditions | Powered by Tradie Web Guys